Whilst carrying out a pre-lift inspection, the operator noticed that a bolt on the D-link was not correctly fitted. Failure to spot and correct this could have resulted in a serious injury or fatality.
This alert is a reminder of the critical importance of proper planning, communications, and execution during all crane lifting operations.
Recent observations and incidents have highlighted the potential for serious injury, equipment damage, and operational delays when lift procedures are not followed correctly. All personnel involved in crane activities must remain vigilant, adhere to established lifting plans, and ensure that safety controls are in place before, during and after each lift.
The images below show the pin for the shackle had not been properly secured with only a few threads engaged.