Best Practice

LOCATION: Cement ARTICLE YEAR 2011
ACTIVITY: Maintenance & Housekeeping COMPANY: Lafarge Cement UK Ltd
SUB ACTIVITY: N/A COMPANY LOCATION: Aberthaw Works
BEST PRACTICE No: BP763 COMPANY TEL: 01446 752363
COUNTRY OF ORIGIN: United Kingdom
TITLE  
Construction of a precast section arch at the inlet of a kiln.
ARTICLE
Description

Aberthaw Works has developed a new methodology to replace the arch at the inlet of their kiln. The system uses pre-cast sections. The pre-cast sections are manufactured in a controlled environment and cured in a furnace at the recommended temperature. Bolted anchors are placed in the sections before casting, and these are then used install the arch.

Benefits

• The sections are of consistent quality, longer lasting and far less prone to failure
• Removes hazards previously associated with welding and subsequent weld failures
• Operation is a lot quicker minimising exposure to this harsh environment
• The use of vibratory equipment and jack has been eliminated